In impact each measures develops a defined process. The process follows the maturity model. It starts at maturity 0 (DoI: 0; idea) and ends with maturity 6 (DoI: 6; completed). To move to the next DoI (Degree of Implementation), the prerequisites of that DoI must be fulfilled.
Degree of Implementation (DoI) |
|
Requirement per DoI | |||
|
|
DoI 0 |
Idea |
|
New idea has been captured and a gross description of the starting point and objective has been made. |
|
|
DoI 1 |
Identified |
|
Responsibilities defined, gross estimate of potential (top-down) made, implementation risks identified and mutual exclusivity across other initiatives as well as interdependencies are known. |
|
|
DoI 2 |
Detailed |
|
Review by PMO successful, implementation plan and potentials are detailed, relevant documents have been uploaded. |
|
|
DoI 3 |
Approved |
|
Implementation team approved and measure approved for implementation. |
|
|
DoI 4 |
Started |
|
Ressources have been provided and implementation has been started. |
|
|
DoI 5 |
Effective |
|
First major Activities are completed and first effects on P&L or balance sheet are realized (below 100%). |
|
PoI 6 |
Completed |
|
Major Activities have been completed and financial effects are 100% fully effective. |